In addition to our primary manufacture and installation products and services we also offer numerous extras and a comprehensive ongoing servicing contract.

We also welcome your call to discuss any services not listed; we take pride in delivering for our clients whatever their request and believe that our after sales is amongst the best in the business.


Pump Servicing

Additional services include:

  • Site Inspections / Surveys
  • Cleaning / Servicing
  • On site maintenance
  • Rectification work
  • Commissioning
  • Grease traps
  • Drain Surveys
  • Pipework and accessories
  • High / Low Level Alarm systems
  • Access covers and frames
  • All other associated ancilliaries

 

Servicing


To ensure the longevity and efficiency of your sewage and water pumping stations we recommend our ongoing servicing agreement, which includes;

  • Hose or jet-wash the sump-internals/pumps
  • Breakdown and remove crust from surface of water within sump
  • Check pumps for any blockages and remove same
  • Check for free rotation of impellers/visually check condition of same
  • Audibly check motor bearings for noise
  • Check condition of motor oil
  • Strip *volutes to expose impellers & seals
  • Inspect condition of mechanical seals
    *Replenish motor oil as required.
  • Clean and inspect condition of neoprene cabling and glands on pumps and floatswitches
  • Remove inspection covers on non-return valves, check and remove any blockages
  • Check for correct seating of flaps/sealing, lubricate and refit covers
    *Rotate and lubricate isolation valves to ensure correct operation
  • Inspect and note any corrosion to pipework/valves within sump
  • Lift float switches and check correct auto sequence
  • Carry out ‘megger’ test (insulation resistance test) to motor windings noting any low readings
  • Check any electrical junctions/boxes/connectors. Dry out and re-make/re-seal (as required)
  • Carry out clamp-meter tests noting correct running current of pump motors
    *Open control-panel and check for correct movement of motor starter contacts
    Inspect and note wear to same.
    *Check all panel bulbs and audible sounders. Report any replacements required
    *Check discharge stools, guide rails and upper support brackets noting any corrosion
  • Check pump lifting chains, shackles and hooks noting and corrosion.
  • General condition; check and report upon the general condition of sump and access opening

* Where applicable